Winglet
Operation Center Frankfurt
The Operation Center Frankfurt is being built in the service area of Fraport AG where it will be protected by controlled access. Due to this building’s exposed location between the apron and public areas, it will have the special attraction of being right in the middle of activities at the airport. The Operation Center Frankfurt will benefit from close proximity to both terminals and all important infrastructure and facilities such as the ICE train station, shopping areas, food and beverage outlets, conference facilities and much more.
The underground level, ground floor and first three upper stories of the OCF integrate the functions that are directly related to apron activities, such as changing and break rooms, offices and control facilities. Levels 4 to 9 contain offices accessible from the utility zones. Between 40 and 50 workplaces are being implemented on each level in compliance with the applicable regulations. The underground level contains changing facilities for about 950 persons as well as equipment rooms. The building’s parts are accessed via two separate safety stairwells: one in front for the cellar, ground floor and levels 1-3, and another for the upper levels.
The focus is on ensuring the flexibility and efficiency of the offices and optimally meeting the organizational needs of tenants. Offices are being created to provide a quite environment that is conducive to concentrated work, as well as common areas for holding meetings. A transparent design will ensure visual contact and communication between workers.
Space and Building Data
| Gross floor space: | Approx. 13,000 sq.m, above ground: 12,000 sq.m, below ground: 1,000 sq.m |
| Usable space: | Approx. 12,000 sq.m |
| Planning grid: | 1.35 x 1.35 m |
| Configurable units: | Max. of 420 sq.m per unit |
| Parking: | 23 spaces on the utility side, 21 on the apron side |
| Scheduled completion: | 2011 |
Energy consumption will be about 15% less than the ceiling set by the 2009 German Energy Savings Ordinance. The building’s shape is being adapted to that of the C/D Pier, i.e. angled by 45°.
Interior Equipment, Materials and Systems
All offices will have hollow floors; special areas such as control and server rooms will be equipped with double floors. All areas will have wall-to-wall carpeting. The interior multipurpose zone will have a drop ceiling for air distribution. The multipurpose zone will feature glazed partitions, while the offices will have plasterboard partitions. Wood, steel and metal-frame doors will be installed. The offices and control rooms will have drop ceilings with a cooling function and acoustic insulation.
Façades
The north façade will be made of thermally insulated metal with metal strip windows, and the south façade will feature post-and-beam elements. The window strips will be in a 1.35-meter grid to allow flexible partitioning of the office space. The east and west sides will be glazed. The south side will receive outside, motorized sun blinds as well as manually operated blinds on the inside.

- Fraport AG
- Frankfurt Airport Services Worldwide60547Frankfurt am Main
- info@fraport.de